Capital budget works progress
North Burnett Regional Council wishes to advise residents that the kerb and channel replacement works, footpath replacement works and drainage works programmed through Council’s 2017-18 Capital Budget is scheduled to commence in February.
The works are scheduled for the following locations and commencement dates and are expected to take approximately one week at each location, weather permitting:
Biggenden 05-02-18 Drain – Kimber Street
Biggenden 12-02-18 Kerb and Channel – Caroline Street
Gayndah 12-02-18 Kerb and Channel – Anzac Parade
Mundubbera 12-02-18 Footpath – Bouverie Street
Mundubbera 19-02-18 Footpath – Burnett & Leichhardt Streets
Monto 26-02-18 Kerb and Channel – Lister Street
The Kimber Street drainage works will incorporate excavation and shaping of an earth drain to allow for the construction of a concrete path to eliminate water ponding and improve drainage outcomes for local residents.
Affected residents will be notified individually by mail. Due to the nature of the works, during this period access to individual properties may be unavailable and alternate parking arrangement will be required.
To carry out these works safely and efficiently, traffic controllers, closures and speed restrictions will be in place as required, with every effort made to minimise disruptions to residents. Council thanks all residents in advance for their patience and cooperation while these works are underway.
For further information regarding these works, please contact Council’s Senior Technical Officer – Works Programming on 1300 696 272 (1300 MY NBRC) or email Council.